C-2 · Orange Co., FL Code updated Jun 2025 GC · Maricopa, AZ Corridor expansion approved HC · Harris Co., TX Drive-thru stacking updated CB · Mecklenburg, NC FAR bonus program extended B-3 · Cook Co., IL CUP process streamlined BU-2 · Miami-Dade, FL Height limits amended C-2 · Fulton Co., GA Drive-thru by-right confirmed CS · Travis Co., TX New transit overlay effective CB · King Co., WA SEPA threshold raised M-1 · Duval Co., FL FAR increased to 0.50 MUDD · Charlotte, NC South End overlay expanded CG · Hillsborough, FL New drive-thru stacking rules C-2 · Orange Co., FL Code updated Jun 2025 GC · Maricopa, AZ Corridor expansion approved HC · Harris Co., TX Drive-thru stacking updated CB · Mecklenburg, NC FAR bonus program extended B-3 · Cook Co., IL CUP process streamlined BU-2 · Miami-Dade, FL Height limits amended C-2 · Fulton Co., GA Drive-thru by-right confirmed CS · Travis Co., TX New transit overlay effective CB · King Co., WA SEPA threshold raised M-1 · Duval Co., FL FAR increased to 0.50 MUDD · Charlotte, NC South End overlay expanded CG · Hillsborough, FL New drive-thru stacking rules
Abbreviation: CUP

Conditional Use Permit (CUP)

Discretionary approval required for uses that are allowed in a zone only under specific conditions, typically after a public hearing.

Full Definition
A Conditional Use Permit (CUP) — also called a Special Use Permit (SUP) or Special Exception in some jurisdictions — is a discretionary land use approval that allows a use that is *potentially* compatible with a zone, but requires case-by-case review to ensure it meets specific conditions.

?
- ? You file for a building permit and build. No public hearing.
- ? You must apply to the Board of Zoning Adjustment (BZA) or Planning Commission, typically submit site plan, traffic study, and other materials, wait for a public hearing, and receive approval before you can even apply for a building permit.

? 60–120 days minimum, often 3–6 months in larger p5_counties.

?
- Drive-thru restaurants (in B-2/B-3 Cook County IL)
- Auto dealerships adjacent to residential
- Bars and nightclubs (separation requirements from schools, churches)
- Gas stations in some jurisdictions
- Self-storage facilities

? CUP required = entitlement risk. The approval is not guaranteed, can be appealed by neighbors, and adds timeline. Always factor 3–6 months of CUP process into pro forma hold period assumptions.
📐 Practical Example

Drive-thru restaurant in B-2 Cook County requires CUP approval + traffic study before building permit.

How This Appears on ByRightHQ Zone Pages

On every zone detail page, ByRightHQ shows Conditional Use Permit (CUP) data sourced directly from the county LDC. Terms like this one are underlined with a dotted line — hover to see the definition.

See C-2 Orange County FL → (example zone page)
Also known as: conditional use permit · CUP · special use permit · SUP · special exception